Shenhua Ningxia Coal Industry Group chose HQC to design a coal indirect liquefaction processing facility located in the Ningdong Energy Chemical Base in Yinchuan, China.

The largest indirect coal liquefaction construction project in the world, it covers about 728.75 hectares (2.8 square miles) and required an investment of US$10 billion.

"This national demonstration project is a landmark event for China's coal oil and chemical industry and required a huge investment,” explained Zhongyang Li, chief engineer with HQC.

The project includes the coal gasification plant; synthetic oil plant; catalyst plant; and installations for all other processes. Annually, the facility uses 24.5 million tons of coal (raw coal and fuel coal) to produce:

  • 4 million tons of oil
  • 1 million tons of methanol
  • 2.7 million tons of 405 reconcile diesel
  • 1 million tons of naphtha
  • 300,000 tons of liquefied gas
  • Other derivatives

CAESAR II was used to design 13,450 process pipelines and 2,400 pieces of equipment. In operation, the ethylene cracking furnace tube reaches 1100 at 0.5MPa internal pressure, so calculating creep stress is critical. In addition, other pipes and equipment experience severe cyclic conditions.

CAESAR II helped reduce man-hours by 20 percent while avoiding security risks. It also helped avoid overdesign, saving US$1.3 million in materials.

“In China we have an old proverb: A handy tool makes a handy man. CAESAR II gives us accurate stress analysis and optimized design,” Li said.

“By keeping costs within budget, we achieved 100 percent satisfaction feedback from the client. Using CAESAR II has significantly enhanced the reputation of HQC at home and abroad.”

***